Construction company ahead of schedule on Westheimer Road project with less people on the road
Read full article: Construction company ahead of schedule on Westheimer Road project with less people on the roadHOUSTON – Drivers in the Galleria area remember what it's like to drive down Westheimer road near Interstate 610 before the stay-at-home order went into effect. Drivers said there is less traffic on a typically heavily traveled road. Drivers could see light traffic even when the order lifted since road construction companies have been able to work longer hours. Angel Brothers Construction Company is set to finish its nine miles of asphalt pavement project on Westheimer road in 90 days instead of the initially projected 13 months. Derek Angel, who is the co-owner of Angel Brothers, which is contracted with TxDOT to complete the road project, said his crew can work without interruptions.